English / Français

When Inaction Results in a Dismissed Action

Province of New Brunswick v Clayco Construction (2001) Ltd, et al, 2022 NBQB 66.

Read Time: 4 minutes (approx.)

By: Chloe Jardine (Articling Student)

In 2006, the Province of New Brunswick (“the Plaintiff”) awarded a contract to the Clayco Construction (2001) Ltd. (“the Defendant”). This contract was to complete the removal of remaining portions of a bridge crossing the Petitcodiac River in Moncton, New Brunswick. A year later, the Defendant informed the Plaintiff that they were unable to fulfil the contract. In response, the Plaintiff declared the Defendant in default of the contract. There were exchanges between the parties over the next several years, without substantial progress towards a resolution, until the Plaintiff expressed an interest in conducting Examination for Discovery in May 2018.

A motion was then filed by the Defendant to dismiss the Plaintiff’s claim for reason of delay under Rule 26.01(c) of the New Brunswick Rules of Court. The Defendant argued that an inexcusable delay of nine years and five months was entirely attributable to the Plaintiff, and the death of a key witness, Douglas Tucker, during this period would result in serious prejudice to their defence. The Plaintiff conceded that approximately four years of delay was unjustifiable but argues that this did not constitute an excessive delay. Understaffing, the volume of documents traditionally involved in construction litigation, and limited resources were all cited as rationale for the delay. Further, the Plaintiff argued that the Defendant did not suffer prejudice because other witnesses were available that had been present and could adequately articulate the position of the late Mr. Tucker.

The Defendants needed to establish that there had been an inordinate delay, that this inordinate delay was inexcusable, and that the Defendant was likely to be seriously prejudiced by this inordinate delay. The Court found that the delay by the Plaintiff did constitute an inordinate delay, and that the small number of relevant documents and resources of the Plaintiff’s legal department made the delay inexcusable. Additionally, the loss of Mr. Tucker during the delay was found to seriously prejudice the Defendant’s case. The Court went further to say that even if the loss of Mr. Tucker had not constituted serious prejudice, that this third factor would still be satisfied by inferred prejudice to the Defendant.

The Court dismissed the Plaintiff’s argument that a subsequent contract for the work had to be completed to determine the value of damages and progress the litigation. The Court found that the Plaintiff demonstrated that the substantial delay would result in serious prejudice to their defence and dismissed the Plaintiff’s action against the Defendant.

 

Link: https://www.canlii.org/en/nb/nbqb/doc/2022/2022nbqb66/2022nbqb66.html?autocompleteStr=2022%20NBQB%2066&autocompletePos=1

Related Posts